Assignment:
The “To Complete Performance Index” (TCPI) is a measure of the cost performance required in order to finish the outstanding work within the remaining budget. The formula for this index is
a. BAC – EAC
b. AC + BAC – EV
c. EV/AC
d. (BAC – EV)/(BAC – AC)