The need to manage technical interfaces and to correct incompatibilities is likely to create technical conflicts during the ________ phase of the project lifecycle.
Project formation
Project buildup
Main program
Project phase out

________ problems are comparatively rare during project phase-out because most have been solved or bypassed earlier.
Resource
Schedule
Authority
Technical

Personality conflicts during project phase-out are often caused by ________.
Pressure to complete the project
Anxiety about leaving the project
Pressure to complete the project and anxiety about leaving the project
Distribution of expenses charged to the project

Identify the category of conflict that is not included in the categories used by Thamhain and Wilemon in their study of project conflict.

Differences about goal/expectations
Uncertainty about authority
Interpersonal problems
discipline/problem-orientation differences