Question - McCombs Contractors received a contract to construct a building for a price of $ 700,000, and the company determined that its performance obligation was satisfied over time. Other information relating to the contract is as follows:
|
2017
|
2018
|
Costs incurred during the year
|
150,000
|
242,000
|
Estimated costs to complete
|
350,000
|
168,000
|
Billings during the year
|
120,000
|
250,000
|
Cash collections during the year
|
100,000
|
260,000
|
Required: Compute the amount of gross profit recognized during 2017 and 2018.