Problem:
You are evaluating a project that costs $63,000 today. The project has an inflow of $136,000 in one year and an outflow of $53,000 in two years. What are the IRRs for the project? (Negative answers should be indicated by a minus sign. Do not round intermediate calculations and round your final answers to 2 decimal places. (e.g., 32.16)) IRR Smallest %? Largest %?
What discount rate results in the maximum NPV for this project? (Negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places. (e.g., 32.16)) IRR %?
Note: Explain all calculation and formulas.