Materials quantity variance for the month problem


Question 1: Given the cost formula Y = $12,000 + $6X, total cost at an activity level of 8,000 units would be:

A)    $20,000. C)    $12,000.
B)    $60,000. D)    $48,000.

Question 2: The following materials standards have been established for a particular product:

Standard quantity per unit of output 1.7 meters
Standard price $19.80 per meter

The following data pertain to operations concerning the product for the last month:

Actual materials purchased 5,800 meters
Actual cost of materials purchased $113,680
Actual materials used in production 5,100 meters
Actual output 3,200 units

Question 3: What is the materials quantity variance for the month?

A)    $13,720 U  C)    $13,860 U
B)    $6,732 F    D)    $6,664 F