Master schedule-productivity standards


You have just taken over the general manager position for a very well-known restaurant in the area. During the interview process, one of the key items discussed was the importance of controlling labor costs. The current owners feel that a master schedule needs to be developed to help meet the labor cost budget and ensure maximum productivity from the staff. They have asked you to create a master schedule, based upon the productivity standards (a top priority).

You will need the following information to create the master schedule: 

  • Maximum seating capacity of the restaurant: 250 guests 
  • Hours of operation: 11 a.m.–11 p.m. 
  • Productivity standards for the following departments: 
    • Servers ratio: 12 to 1 (i.e., 1 server can take care of 12 guests per time period) 
    • Host ratio: 60 to 1 
    • Bussers ratio: 75 to 1 
    • Cooks ratio: 30 to 1 
    • Dish washers ratio: 100 to 1 

TIME PERIOD 

GUESTS 

11–12 

45 

12–1 

150 

1–2 

140 

2–3 

50 

3–4 

35 

4–5 

40 

5–6 

65 

6–7 

125 

7–8 

200 

8–9 

175 

9–10 

100 

10–11

25 

TOTAL GUESTS 

1,150 

Create the master schedule.

Solution Preview :

Prepared by a verified Expert
Operation Management: Master schedule-productivity standards
Reference No:- TGS058626

Now Priced at $20 (50% Discount)

Recommended (94%)

Rated (4.6/5)

E

Expert

2/13/2016 5:31:46 AM

The solution is done in MS excel with sowing all the calculation on all about Master Schedule. In the solution of given problem Labor Servers Host Bussers Cooks Dish Washers has been calculated.