Mary is the project manager for a web design project for


Mary is the project manager for a web design project for Newberry Pet Foods. So far in the six weeks (of the twelve week project), Mary’s team has completed five tasks which had a combined planned value of $8800. However, the team spent $9200 to complete those tasks. She has five additional tasks to complete the project. What are the PV, EV, AC, CV, SV, CPI, and SPI for Mary’s project?