Market Company uses a typical two card kanban production system. Inventory levels are roughly proportional to the number of Kansans. For one part, the average usage rate is 1,400 parts per day, container size is 50 parts, and cycle time per batch is 2 hours. Mark is ultimately working to reduce the lead time to 100 minutes. Assuming no safety stock is carried, what effect would this have on average inventory?