Question: You are about to begin managing the fourth phase in a project. the prior three phases are running behind schedule and you want to make it clear that you are not accountable for the tardiness of the tasks from the prior phases. you decided to create an interim plan for the tasks in phase 4. what entries do you need to make to describe where the interim bars should appear? blank 1 refers to where the interim bar begans and blank 2 refers to where the interim bar ends