Managerial Report Prepare a report for Chris Lane. Your report should include, at a minimum, the following items: 1. A schedule that will enable each of the 18 couples to play every other couple over the 17-week season. 2. A contingency schedule that can be used if the couple that contacted Chris decides to cancel for the season