Maintenance costs at Planet Corporation factory are listed below:


Machine-Hours

Maintenance Cost

April

3,135

$48,340

May

3,095

$47,993

June

3,133

$48,345

July

3,157

$48,548

September

3,065

$47,733

October

3,084

$47,880

November

3,125

$48,247

December

3,098

$48,014

Management believes that maintenance cost is a mixed cost that depends on machine-hours.

Use the high-low method to estimate the variable and fixed components of this cost.

What is the variable cost per unit?
What is the fixed cost?