1. Which describes the various challenges provided by teams in the workforce.
2. Describe one qualitative tool or technique that can be used to estimate activity durations of the critical path of a project schedule?
3. Little’s Law Firm has two paralegals. Customers arrive randomly at an average rate of 10 per hour. Service times have a mean of 10 minutes and a standard deviation of 10 minutes. What is the average total time a customer spends in the system?