Liquidated damages clause in a contract


Question: A liquidated damages clause in a contract for any sale of goods will not be enforced when

1. actual damages would be easy to prove in the event of a breach

2. the amount specified is so large as to be a penalty

3. the amount specified is so low as to be uncomscionable

4. all of the above