Line Balancing Procedure in Assembly Layout
- step1: Determine what tasks must be performed to complete one unit of a finished product and the sequence in which the tasks must be performed draw the precedence diagram.
- Step 2: Estimate the task time amount of time it takes a worker to perform each task)
- Step 3: Determine the cycle time (the amount of that would elapse between products coming off the end of the assembly line, if the desired hourly production were being produced)
- Step 4: Assign each task to a worker and balance the assembly line. This process results in determining the scope of each worker job or which tasks that the he or she will perform.