[a] A process currently consists of 3 activities A, B, C performed in sequence. The current defect rate at activity A is 20%. The location in the process (after A, B, or C) where the defects are detected has no impact on flow time or throughput as long as the defect rate at activity A remains 20%.
True/False
[b] Limiting the maximum size of work in process buffers between stages of a process results in a pull system.