Let’s assume 3M produces “Command Hooks” at a rate of 10,000 units per day. Before reconfiguring their production process, their flow time through the process was 100 days. After reconfiguring, the new flow time is 35 days. After reconfiguring, how many units of work in progress inventory are in the process?
< 100,000
Between 100,000 and 300,000
Between 300,000 and 600,000
Between 600,000 and 900,000
>900,000