Les is concerned that his variable cost per unit projection for a project may not be reliable. Which type of analysis will help him determine the effect that an incorrect variable cost estimate will have on the final outcome of the project?
a. Monte Carlo simulation
b. Financial break-even analysis
c. Sensitivity analysis
d. Contribution margin analysis
e. Scenario analysis