Problem - As a test case, City A has decided to pursue regulatory approaches to controlling CO2 in B town, where CO2 emissions primarily come from local electricity generation. There are three power plants in B town, and each has submitted their estimated abatement costs for CO2.
Plant 1: Gas Plant releasing 2,400,000 tons of CO2/year
Abatement Approach
|
Tons Removed/Year
|
Cost per Ton
|
Carbon Sequestation
|
30,000
|
$20
|
Heat Rate Improvement
|
1,200,000
|
$50
|
Efficiency Improvement
|
95,000
|
$70
|
Increase in lower emitting capacity
|
2,500
|
$190
|
Plant 2: Gas Plant releasing 90,000 tons of CO2/year
Abatement Approach
|
Tons Removed/year
|
Cost Per Ton
|
Efficiency Improvement
|
18,000
|
$35
|
Carbon Sequestrain
|
12,000
|
$45
|
Fuel switching/construction of wind Capacity
|
40,000
|
$130
|
Plant 3: Coal Plant releasing 2,740,000 tons of CO2/year
Abatement Approach
|
Tons Removed/Year
|
Cost Per Ton
|
Carbon Sequestration
|
26,000
|
$30
|
Efficiency Improvements
|
70,000
|
$60
|
Fuel Switching
|
190,000
|
$85
|
Waste Heat Recovery
|
540,000
|
$140
|
B wants to reduce CO2 emissions by 1,569,000 tons per year (approximately a 30% reduction). They are looking at alternative approaches to achieving this goal, and are interested in comparing the costs of command-and-control to the least-cost solution to achieving this abatement level.
a) Command-and-control: Each plant must reduce their annual CO2 emissions by 30%. Please complete the following table.
|
Plant 1
|
Plant 2
|
Plant 3
|
Total
|
Eliminated Emissions(tons)
|
|
|
|
|
Remaining emissions (tons)
|
|
|
|
|
Total cost of abatement
|
|
|
|
|
b) Least-Cost solution: What is the least cost at which the 30% abatement level could be achieved? Complete the following table to indicate how much each plant would abate and the costs of this abatement using least-cost methods.
|
Plant 1
|
Plant 2
|
Plant 3
|
Total
|
Eliminated emissions (Tons)
|
|
|
|
|
Remaining emissions (Tons)
|
|
|
|
|
Total cost of abatement
|
|
|
|
|
c) What policies might you recommend to arrive at the least-cost solution? What are some of the pros and cons of each?