Land, Buildings, and Machinery.
A company made the following expenditures in connection with the construction of its new building:
Architect's fees for the new building.......................................
|
$12,000
|
Cash-paid for land and run-down building of the land.........
|
300,000
|
Removal of old building.............................................................
|
18,000
|
Salvage from sale of old building materials............................
|
(4,000)
|
Construction survey to site the new building.........................
|
1,500
|
Legal fees for the title search....................................................
|
3,000
|
Excavation for the basement construction.............................
|
25,000
|
Machinery purchased for operations.......................................
|
100,000
|
Storage charges on machinery because building was not ready when machinery was delivered................................................
|
900
|
Freight in machinery purchased...............................................
|
1,600
|
Hauling charges to delivery machinery from storage to new building.........................................................................................
|
300
|
Construction costs of new building..........................................
|
1,000,000
|
Landscaping.................................................................................
|
20,000
|
Installation of machinery...........................................................
|
2,500
|
Prepare a schedule showing the amounts to be recorded as Land, Buildings, and Machinery.