Lakeside Inc. manufactures four lines of remote control boats and uses activity-based costing to calculate product cost.
Activity Cost Pool |
Estimated Total Cost |
Estimated Cost Driver |
Machining |
$ |
324,000 |
13,100 |
machine hours |
Setup |
|
68,000 |
440 |
batches |
Quality control |
|
96,000 |
900 |
inspections |
Compute the activity rates for each of the following activity cost pools: (Round your answers to 2 decimal places.)
Machining |
|
Per Machine Hour |
Setup Costs |
|
Per Batch |
Quality Control |
|
Per Inspection |