Labor of this activity is given as in the crew 1 brick


A masonry project requires 900 sf repointing. Labor of this activity is given as in the CREW, 1 brick mason and 1 helper. The productivity is 0.5 labor hours per 1 sf. The wages are for the mason $60 and for the helper $45 per hour. what will be The cost of labor in dollars.