Which one of the following tasks is least likely to be performed by a strategic management accountant when understanding knowledge management activities at the end of a project?
A. Enhancing organizational learning about cost and budget variances
B. Assessing the effectiveness of the project's non-financial performance measures
C. Calculating the project's earned value (EV)
D. Analyzing problems that arose during the project
Additional Requirement
This multiple choice question based on the Corporate Strategy and describe about the tasks being performed by strategic management accountant while understanding knowledge management activities at the end of a project.