Problem-
Kiner, Inc. began work in 2012 on a contract for $12,600,000. Other data are as follows:
|
2012
|
2013
|
Costs incurred to date
|
$5,400,000
|
$8,400,000
|
Estimated costs to complete
|
3,600,000
|
|
|
|
|
Billings to date
|
4,200,000
|
12,600,000
|
Collections to date
|
3,000,000
|
10,800,000
|
Kiner, Inc. began work in 2012 on a contract for $12,600,000. Other data are as follows:
If Kiner uses the completed-contract method, the gross profit to be recognized in 2013 is
a. $2,040,000.
b. $4,200,000.
c. $2,100,000.
d. $8,400,000.
Additional information-
This problem related to Basics Accounting and calculation of profit using completed contract method.