Question: Seven Jobs must be processed in two operations: A and B. All Seven jobs must go through A and B in that sequence – A first, then B. Determine the optimal order in which the jobs should be sequenced through the process using these times:
Job
|
Process A Time
|
Process B Time
|
1
|
9
|
6
|
2
|
8
|
5
|
3
|
7
|
7
|
4
|
6
|
3
|
5
|
1
|
2
|
6
|
2
|
6
|
7
|
4
|
7
|