Problem:
Our cost per jet in terms of materials is 1.00 per and the labor is .50. Our total annual overhead is estimated to be $20000 and our overhead seems to be related to the number of jets we produce. Can you work me up the total costs for our order of 70 jets?
Which system is a better choice between a job or a process cost accounting systems?