Q1.____ involves allocating ownership of the risk to another party.
a. Risk exploitation
b. Risk sharing
c. Risk enhancement
d. Risk acceptance
Q2. A project manager can chart the probability and impact of risks on a ____.
a. risk ranking chart
b. risk probability table
c. probability/impa.