Question - Sully Company uses 3,000 yards of canvas each day to make tents. It usually takes ten days from the time Sully orders the material to when it is received. If Sully's desired safety stock is 12,000 yards, what is Sully's order point?
a. 12,000 yards
b. 21,000
c. 30,000 yards
d. 42,000