It plans to use this production line sixteen hours a day in


Your scientists have perfected Harry Potter's invisibility cloak and are ramping up production. It plans to use this production line sixteen hours a day in order to meet projected demand of 1575 units.

The tasks necessary to produce this product are:

Task Time (minutes) Predecessor
Get Cloth 6 none
Get Bat Wings 6 none
Boil Toil and Trouble 16.6 none
Stir in ingredients 1 Bat Wings & Boil
Paint onto Cloth 13.0 Stir & Cloth
Package for delivery 4.0 Paint

If the company wants the output rate to be equal to demand, what is the desired cycle time (in seconds)?