A project plan developed in MS Project has over committed resources. Resource leveling may or may not increase the duration of the project, but can not decrease the duration of the project.
True
False
In order to successfully implement a PMO a firm must first develop a detailed project management methodology.
True
False
It is important to develop a change control process before the project starts.
True
False
Since most projects don't have changes to scope, it is not necessary to develop a change control process before the first change is identified.
True
False