Question: In Problem, for each solution, (a)-(e), determine which jobs are delivered on time and which jobs are tardy.
Problem: It is currently day 10 in the production calendar of the XYZ Machine Shop. Three orders (A, B, and C) are to be processed at a particular machine tool. The orders arrived in the sequence A-B-C. The following table indicates the process time remaining and production calendar due date for each order.
![1014_Order.png](https://secure.tutorsglobe.com/CMSImages/1014_Order.png)
Determine the sequence of the orders that would be scheduled using the following priority control rules:
(a) first-come-first-served,
(b) earliest due date,
(c) shortest processing time,
(d) least slack time, and
(e) critical ratio.