(a) Analyse the timing and resource use of the project described by the following values.

(b) It costs €1,000 to reduce the duration of an activity by 1. If there is €12,000 available to reduce the duration, what is the shortest time the project can be completed within? What are the minimum resources needed by the revised schedule?