Project A: Investment Required $160,000 Net Present Value: $44, 323 Life of Project in Years: 7 Initial Rate of Return: 18%
Project B $135,000 $42,000 12 16%
Project C $100,000 $35,035 7 20%
Project D $175,000 $38,136 3 22%
Project profitability index for each project would be?
In preference rank : net present value, project profitability index, and internal rate of return
Which ranking do you prefer? Why?