3. In your own words, explain the difference between hard logic and soft logic for establishing dependency relationships in project schedules. Offer a creative example (not from the chapter) of each one. 4. Explain the relationships among project deliverables, work packages, and mile- stones as they would appear in a schedule. Use your own words and examples.