The following jobs are waiting to be processed at Julie Morel's machine center:

Job

Date Order Received

Production Days Needed

Date Order Due

A

110

20

180

B

120

30

200

C

122

10

175

D

125

16

230

E

130

18

210

In what sequence would the jobs be ranked according to the following rules: (a) FCFS, (b) EDD, (c) SPT, and (d) LPT? All dates are according to shop calendar days. Today on the planning calendar is day 130, and none of the jobs have been started or scheduled. Which rule is best?