In what sequence would the jobs be ranked according to the


An Alabama lumberyard has four jobs on order, as shown in the following table. Today is day 205 on the yard's schedule.

Job

Due Date

Remaining Time (Days)

A

212

6

B

209

3

C

208

3

D

210

8

In what sequence would the jobs be ranked according to the following decision rules:

a) FCFS

b) SPT

c) LPT

d) EDD

e) Critical ratio

Which is best and why? Which has the minimum lateness?