In what sequence would the jobs be ranked according to the


The following jobs are waiting to be processed at the same machine center. Jobs are logged as they arrive:

Job

Due Date

Duration (Days)

A

313

8

B

312

16

C

325

40

D

314

5

E

314

3

In what sequence would the jobs be ranked according to the following decision rules: (a) FCFS, (b) EDD, (c) SPT, and (d) LPT? All dates are specified as manufacturing planning calendar days. Assume that all jobs arrive on day 275. Which decision is best and why?