In the year 2012 utica construction company contracted to


In the year 2012, Utica Construction Company contracted to build a warehouse for $6,000,000. Data relating to the contract are as follows:

2012 2013

Costs incurred during the year $1,000,000 $3,000,000
Estimated costs to complete as of year end $3,000,000 -
Billings during the year $3,000,000 $3,000,000
Cash collections during the year $2,500,000 $3,500,000

Determine the gross profit that Utica Construction should recognize in both 2012 and 2013 using

i) the completed contract method

Solution Preview :

Prepared by a verified Expert
Accounting Basics: In the year 2012 utica construction company contracted to
Reference No:- TGS0774033

Now Priced at $10 (50% Discount)

Recommended (91%)

Rated (4.3/5)