Question: In the previous problem, if each workstation is 6.2 in long, and the tolerance time Tt = cycle time Te, determine the following:
(a) speed of the conveyor,
(b) center-to-center spacing be-tween units on the line,
(c) total length of the trim-chassis-final line, assuming no vacant space between stations, and
(d) elapsed time a work unit spends in trim-chassis-final.