In the Lulu Hypermarket chain, the daily demand for Product X is normally distributed with a mean of 9000 items and a standard deviation of 1900 items. The lead time is eight days. If the Lulu Hypermarket Manager wants to limit the probability of a stockout to 2%, determine the re-order point.