In problem the current line has an operating cost of 660jhr


Question: In Problem, the current line has an operating cost of $660J/hr. The starting workpart is a casting that costs $4.50/pc. Disposable tooling costs $1.25/pc. The proposed storage buffer will add $6.00/hr to the operating cost of the line. Does the improvement in production rate justify this cost increase?

Problem: A two-week study has been performed on a 12-station transfer line that is used to partially machine engine heads for a major automotive company. During the 80 hr of observation, the line was down a total of 42 hr, and a total of 1689 parts were completed. The accompanying table lists the machining operation performed at each station, the process times, and the downtime occurrences for each station. Transfer time between stations is 6 sec. To address the downtime problem, it has been proposed to divide the line into two stages, each consisting at six stations. The storage buffer between the stages would have a storage capacity 01 20 parts. Assuming the upper-bound approach and a constant downtime, determine:

(a) line efficiency and production rate of current one-stage configuration and

(b) line efficiency and production rate of proposed two-stage configuration.

(c) Given that the line is to be divided into two stages, should each stage consist of six stations as proposed, or is there a better division of stations into stages? Support your answer.

2259_Operation 1.png

Request for Solution File

Ask an Expert for Answer!!
Management Theories: In problem the current line has an operating cost of 660jhr
Reference No:- TGS02248865

Expected delivery within 24 Hours