1. In backward loading to infinite capacity . . . .
a) Due dates are estimated
b) Capacity cannot be exceeded
c) Required capacity is found
d) The purpose is to find the approximate completion date
2. Measuring all internal resources based on high levels of utilization or efficiency is a good example of:
a) A behavior constraint
b) A type of Throughput constraint
c) Exploitation
d) Subordination
e) All the above