If uniform deterministic processing of vehicles collecting


Vehicles arrive at a recreational park booth at a uniform deterministic rate of 5 veh/min.

If uniform deterministic processing of vehicles (collecting of fees) begins 20 minutes after the first arrival and the total delay is 3200 veh-min, how long after the arrival of the first vehicle will it take for the queue to be cleared?