If there is a penalty of 5000 a week for each week the


The project described in the following table has just begun. It is scheduled to be completed in 11 weeks.

a. If you were the manager of this project, would you be concerned? Explain.

b. If there is a penalty of $5,000 a week for each week the project is late, what is the probability of incurring a penalty of at least $5,000?

Activity

Estimated Time(weeks)

Standard Deviation (wks.)

1-2

4

0.70

2-4

6

0.90

1-3

3

0.62

3-4

9

1.90

Request for Solution File

Ask an Expert for Answer!!
Operation Management: If there is a penalty of 5000 a week for each week the
Reference No:- TGS01235031

Expected delivery within 24 Hours