If the rate is increased by 1 the npv of the project falls


Using an interest rate of 10% per year the net present value (NPV) of a project has been correctly calculated as $50. If the rate is increased by 1% the NPV of the project falls by $20. What is the internal rate of return (IRR) of the project?