This year, Benson inc. will produce 57,600 hot water heaters at its plant Yulee,Florida, in order to meet expected global demand. To accomplish this, each labourer at the Yulee plant will work 160 hours per month. If the labourer productivity at the plant is 0.15 hot water heaters per labour hour, how many laburers are employed at the plant?