If the fcfs rule is applied for sequencing the jobs what


Process times for four jobs A, B, C and D that came in that sequence are: 3, 2, 8 and 4 respectively. If the FCFS rule is applied for sequencing the jobs, what would be the percent utilization (rounded to 2-place of decimals)?