For the network shown in Figure P12-24 with all times indicating weeks, answer the following questions
a. What is the impact on the end date of the project if activity B slips by two weeks?
b. What is the impact on the end date of the project if activity E slips by one week?
c. What is the impact on the end date of the project if activity D slips by two weeks?
d. If the customer offered you a bonus for completing the project in sixteen weeks or less, which activities would you focus on first as part of compression ("crashing") analyses?