If the company wants the output rate to be equal to demand


A company is designing a product layout for a new product. It plans to use this production line to meet projected demand of 345 units per 7.50 hour day. The tasks necessary to produce this product are: Task Time (sec) Predecessor u 31 none v 26 u w 2 v x 21 u, v y 58 x z 26 v, y If the company wants the output rate to be equal to demand, what is the desired cycle time (in seconds)? (Keep one decimal place in your answer)

Request for Solution File

Ask an Expert for Answer!!
Operation Management: If the company wants the output rate to be equal to demand
Reference No:- TGS02923436

Expected delivery within 24 Hours