A company is designing a product layout for a new product. It plans to use this production line to meet projected demand of 345 units per 7.50 hour day. The tasks necessary to produce this product are: Task Time (sec) Predecessor u 31 none v 26 u w 2 v x 21 u, v y 58 x z 26 v, y If the company wants the output rate to be equal to demand, what is the desired cycle time (in seconds)? (Keep one decimal place in your answer)