With the information provided can you please tell me how to obtain the safety stock?.
DEMAND= 50,000/YEAR
ORDERING COST= $35/ORDER
HOLDING COST= $2/ UNIT/ YEAR
AVERAGE LEAD TIME= 3 WEEKS
STANDARD DEVIATION= 125 UNITS
90% CYCLE SERVICE
If petromax wants to provide a 90% cycle service level, what should be the safety stock and reorder point?