Question - A company manufactures 1,000,000 units of a product yearly. A new design of the product will reduce materials cost by 12%, but will increase processing cost by 2%. If materials cost is $1.20 per unit and processing will cost $0.40 per unit, how much can the company afford to pay for the preparation of making the new design and making changes in equipment?